What should I do if a solar installer cannot provide a clear interconnection timeline?
Answer
Do not treat the project schedule as firm. Ask the installer to identify the current application status, utility-controlled milestones, assumptions, and customer obligations in writing; independently confirm the status with the utility where possible.
Key points
- Request the application submission date, tracking number, current stage, outstanding items, and expected next decision.
- Separate installer-controlled work from utility-controlled review, study, meter, and permission-to-operate milestones.
- Ask what happens if approval, upgrades, or permission to operate takes longer than expected.
- Consider proposals that provide clearer responsibilities, milestone reporting, and cancellation or delay protections.
What it depends on
- Whether an application has actually been submitted
- Utility process and current queue
- Project size and upgrade requirements
- Contract terms and payment schedule
Risks and trade-offs
- A vague timeline can conceal that no application has been filed.
- You may face storage, financing, rebate, or construction deadlines that the installer cannot control.
- Delaying a project to obtain better certainty may affect pricing or incentive availability.
Information you may need
- Application or case number
- Written utility correspondence
- Contract milestones and delay remedies
- Current equipment and permit status
Your next step
What to do next
Pause any irreversible commitment until you receive verifiable application status and a written schedule with assumptions and responsibilities.