What can cause a solar interconnection application to be delayed?
Answer
Delays can result from incomplete applications, design changes, missing permits, utility workload, required studies, transformer or grid constraints, inspection failures, metering, or communication gaps.
Key points
- Responsibility for each delay should be tracked.
- A complete single-line diagram and accurate equipment data help.
- Utility approval and permission to operate are separate milestones.
What it depends on
- Utility process
- Application quality
- Grid and site conditions
Risks and trade-offs
- Savings may start later than expected.
- Equipment or incentive deadlines may be affected.
Information you may need
- Application status
- Utility requests
- Contract schedule and delay provisions
Your next step
What to do next
Request a written milestone log identifying the current blocker, responsible party, and next required action.