How should a small business assess interconnection risk for a larger commercial solar array?
Answer
Treat interconnection as a feasibility workstream separate from equipment procurement: document the facility's load, service, export profile, and utility study requirements before making major commitments.
Key points
- Assess peak demand, operating hours, seasonal load, backup generation, batteries, and planned expansion.
- Confirm service voltage, transformer and switchgear limits, protection requirements, metering, and export controls.
- Build schedule and financial scenarios for approval, upgrade, curtailment, and delayed operation.
What it depends on
- Facility load profile and one-line diagram
- Array, storage, and export-control design
- Utility study process and available capacity
- Business operating schedule and financing
Risks and trade-offs
- Utility upgrades can materially change cost and schedule.
- An export-limited system may reduce revenue or savings but lower interconnection exposure.
- Construction or financing commitments made before study results can create stranded costs.
Information you may need
- Interval load data and utility bills
- Existing electrical drawings and service information
- Preliminary system and operating design
- Utility study scope, milestones, and cost allocation
Your next step
What to do next
Engage a qualified commercial solar engineer and the utility for a documented pre-application or feasibility review before authorizing equipment purchase or construction.