Answer
Determine this through the utility's interconnection screening or study using the proposed export capacity, service characteristics, and local network conditions. Nameplate system size alone does not establish available connection capacity.
Key points
- Provide the utility with system and inverter ratings, expected export, service voltage, phases, and point of connection.
- Ask whether export controls, storage, or a smaller inverter rating can keep the project within available capacity.
- The utility may require a study to evaluate feeder, transformer, protection, voltage, and reverse-power impacts.
- A commercial project may need engineering documents and a formal capacity or impact assessment.
What it depends on
- Utility network capacity
- Service size and configuration
- Inverter and export-control settings
- System size and operating profile
- Existing generation or large loads nearby
Risks and trade-offs
- A capacity limitation may require curtailment, upgrades, a smaller system, or a different connection point.
- An export-limited design may reduce energy sales or expected savings.
- Informal estimates are not a substitute for utility approval.
Information you may need
- Utility and service details
- System and inverter specifications
- Expected maximum export
- Single-line diagram and site plan
- Existing and planned large loads
Your next step
What to do next
Request a utility pre-application screen or formal interconnection study and have the engineer model both unrestricted and export-limited designs.