What should I ask the utility before signing a contract for a large solar system?
Answer
Ask the utility to confirm the interconnection process, export capacity, study requirements, likely upgrades, costs, schedule, operating limits, metering, and permission-to-operate conditions before signing an irreversible contract.
Key points
- Ask whether the proposed size and point of connection are eligible for the intended export arrangement.
- Confirm application fees, deposits, study requirements, upgrade responsibility, and cost-allocation rules.
- Ask about curtailment, export limits, protection requirements, telemetry, metering, and outage behavior.
- Obtain a case number or written pre-application response and identify what remains uncertain.
What it depends on
- Utility and network configuration
- System size and export profile
- Service voltage and connection point
- Storage and control equipment
- Commercial contract and financing structure
Risks and trade-offs
- Large systems may face more extensive studies, upgrades, and schedule uncertainty.
- Export limits can reduce expected revenue or require controls.
- A contract signed before utility review may leave the customer responsible for major changes.
Information you may need
- Utility pre-application materials
- System one-line diagram and equipment list
- Expected export and operating profile
- Upgrade and study cost estimates
- Contract contingencies
Your next step
What to do next
Complete the utility's pre-application or screening process and make the contract contingent on acceptable interconnection terms.