What should I do if a solar proposal does not clearly identify who handles permits and inspections?
Answer
Do not rely on an implied responsibility. Require the proposal or contract to name the party responsible for each permit, inspection, utility submission, correction, fee, and final approval.
Key points
- Separate building, electrical, structural, fire, zoning, preservation, and interconnection responsibilities where applicable.
- Identify who schedules inspections and who pays for reinspection or corrections caused by the installer.
- Require copies of approvals, inspection results, and permission to operate before final completion.
What it depends on
- Project scope and installation method
- Local permit and inspection process
- Contract terms and exclusions
- Whether subcontractors are used
Risks and trade-offs
- Unclear responsibility can cause delays, surprise fees, and disputes over incomplete work.
- An installer may describe permitting as included while excluding specific approvals.
- Final payment before documentation is complete reduces leverage.
Information you may need
- Detailed proposal and contract
- Permit checklist for the property
- Names of responsible installer and subcontractors
- Required completion and approval documents
Your next step
What to do next
Send the installer a written responsibility matrix and ask for an amended proposal stating who obtains, pays for, and resolves each approval and inspection.