What should a business include in a solar installation contract about operational disruption?
Answer
The contract should define permitted work hours, access, shutdowns, noise, deliveries, safety controls, communication, protection of customers and employees, restoration of affected areas, and responsibility for losses caused by avoidable disruption. It should include a coordinated schedule and an escalation process for urgent operational issues.
Key points
- Identify critical operations, equipment, access routes, loading areas, and blackout-sensitive systems.
- State when electrical shutdowns may occur, their maximum duration, and required notice.
- Assign responsibility for temporary protection, cleanup, damage, security, and restoring operations.
- Require the installer to coordinate subcontractors and maintain appropriate site controls.
What it depends on
- The business's operating hours and critical loads
- The installation method and required electrical work
- The site's safety, access, and emergency procedures
Risks and trade-offs
- Minimizing disruption may require work outside normal hours and increase cost.
- Unplanned shutdowns can affect revenue, inventory, safety, and data systems.
- A vague consequential-loss waiver may leave the business exposed to operational losses.
Information you may need
- A site-specific disruption and shutdown plan
- Business continuity, insurance, and loss-allocation terms
- Notice contacts and emergency escalation procedures
Your next step
What to do next
List critical operations and prohibited or restricted work periods, then incorporate an approved disruption plan and shutdown procedure into the contract.