How should a small business evaluate a proposal that requires it to supply temporary power during solar installation?

Answer

Treat temporary power as a project cost and operational dependency that must be specified, priced, and risk-managed. Determine the loads, duration, connection method, fuel or electricity cost, safety controls, maintenance, noise, emissions, and responsibility for failure, then compare the arrangement with installer-provided power or phased work.

Key points

  • Require a load list, demand estimate, one-line or connection description, and duration.
  • Clarify whether temporary power serves construction tools, critical business loads, controls, or the whole facility.
  • Price equipment rental or purchase, fuel, testing, operator time, maintenance, permitting, and restoration.
  • Set requirements for grounding, protection, inspection, refueling, emergency response, and backup.

What it depends on

  • Required loads and continuity needs
  • Installation phases and outage schedule
  • Site electrical system and available capacity
  • Business safety, environmental, and operating requirements

Risks and trade-offs

  • Undersized or poorly connected temporary power can damage equipment or interrupt operations.
  • Generator-based solutions may create noise, emissions, fuel, and fire risks.
  • Owner-supplied power can shift technical and outage responsibility from the installer to the business.

Information you may need

  • Installer temporary-power specification
  • Critical-load list and operating schedule
  • Connection and protection plan
  • All direct and indirect costs
  • Responsibility for inspection, fuel, failures, and restoration

Your next step

What to do next

Ask the installer for a complete temporary-power plan and at least one priced alternative, then have the business's electrical professional review compatibility and safety.