Payback is delayed because the system receives fewer first-year savings while most or all of the investment has already been made. Quantify the lost first-year production and savings, then shift the subsequent cash flows to the actual commissioning date rather than assuming a full first year.

Key points

  • A delayed start reduces first-year energy savings and may affect financing or contract obligations.
  • The effect is larger when the delay overlaps a high-production season or a period of high electricity use.
  • Separate construction delay, permission-to-operate delay, equipment failure, and expected seasonal variation.
  • Any contractual compensation or remedy should be modeled separately from operating savings.

What it depends on

  • Commissioning date and expected production start
  • Seasonal production profile
  • Electricity use and import-export valuation
  • Financing and payment schedule
  • Any documented provider obligations

Risks and trade-offs

  • A short delay may have a small lifetime effect but a larger cash-flow effect.
  • A production estimate that already assumes a partial first year should not be reduced again.
  • Unresolved commissioning issues can indicate broader performance or approval risks.

Information you may need

  • Contracted and actual commissioning dates
  • Monthly production estimate
  • Payment and financing schedule
  • Evidence of lost production or applicable contractual remedy

Your next step

What to do next

Recalculate the cash flow using actual operation dates and monthly production, then check the contract for responsibility and remedies.