Answer
Evaluate only the period in which the system was operational, then compare production with a time-matched expectation for that commissioning date and the actual weather, outages, shading, and system availability. Do not compare a partial year's total directly with a full-year estimate without adjusting the period.
Key points
- Use the actual permission-to-operate or commissioning date defined by the contract, not merely the installation date.
- Account for startup delays, monitoring gaps, commissioning tests, and partial-day operation.
- Compare monthly or daily performance with a model or historical baseline for the same dates.
- Annualization from a short period is uncertain, especially near seasonal transitions.
What it depends on
- The contractual commissioning and evaluation dates
- Reliable production and availability records
- Weather and irradiance during the operating period
- System configuration and any early defects or outages
Risks and trade-offs
- A short period may not represent annual performance.
- Seasonal production varies substantially, so simple multiplication can mislead.
- Production may be reduced by commissioning issues that should be analyzed separately from weather.
Information you may need
- Commissioning, permission-to-operate, and first-production dates
- Daily or hourly production data
- System estimates and their calculation assumptions
- Weather, outage, shading, and maintenance records
Your next step
What to do next
Define the valid operating window and compare its weather-adjusted production with a date-matched forecast before drawing an annual-performance conclusion.