What happens if the utility requires a different interconnection design after the solar contract is signed?
Answer
The project may need redesign, added equipment, changed export limits, a service upgrade, or cancellation if the contract permits it. Responsibility for cost and schedule depends on the solar contract, change-order terms, interconnection application, and utility requirements.
Key points
- Utility approval is often separate from the sales contract and may occur after signing.
- A revised design can affect system size, production, price, financing, and incentives.
- The contract should state who bears interconnection-study, upgrade, redesign, and cancellation costs.
- Get the revised design and financial effect in writing before authorizing extra work.
What it depends on
- Contract contingencies and change-order provisions
- Utility interconnection determination
- Nature and cost of the required design change
- Financing, incentive, and cancellation terms
Risks and trade-offs
- The customer may face unexpected charges or a less productive system.
- Delaying a decision can affect installation timing and incentive eligibility.
- Accepting an undocumented change makes later disputes harder to resolve.
Information you may need
- Signed contract and all attachments
- Utility study results or written design requirement
- Revised scope, price, schedule, production estimate, and financing terms
Your next step
What to do next
Pause approval of additional work and request a written change order that explains the utility requirement, cost allocation, schedule, and cancellation rights.