How should a contract handle unexpected structural repairs discovered after work begins?
Answer
The contract should require written notice, evidence, a defined approval process, and a priced change order before non-emergency structural work proceeds. It should also distinguish concealed conditions from installer-caused damage and state who bears each cost.
Key points
- Require photographs, technical findings, and a description of why the repair is necessary.
- Specify that the homeowner may obtain an independent assessment or decline the proposed change.
- Require a change order showing scope, price, schedule effect, warranty effect, and payment timing.
- State whether the installer must pause work safely while approval is pending.
What it depends on
- The original structural assumptions and site inspection
- The cause and severity of the discovered condition
- Whether the condition was reasonably discoverable before contracting
- The contract's change-order and cancellation terms
Risks and trade-offs
- Refusing necessary repairs can create safety, water-intrusion, or warranty risks.
- Allowing work without a written price can lead to uncontrolled cost increases.
- An installer may have a conflict if it both diagnoses and profits from the repair.
Information you may need
- The contract's concealed-condition and change-order language
- The installer's written findings and proposed repair
- An independent structural or roofing opinion when the cost or risk is significant
- The effect on schedule, warranty, and financing
Your next step
What to do next
Ask the installer to provide a sample structural change order and agree that no non-emergency repair will begin without your written approval.