How can I tell whether an installer’s promised completion date is realistic?
Answer
Treat the date as realistic only if it is based on identified dependencies, not just an installation-duration estimate. The schedule should separately account for design, equipment delivery, permits, utility approval, inspections, weather, roof work, and correction cycles.
Key points
- Ask for milestone dates and the party responsible for each dependency.
- Confirm whether the date means physical installation, inspection approval, permission to operate, or system activation.
- Look for written assumptions, buffer time, and a process for schedule changes.
- Verify that equipment has been selected and its availability is documented.
What it depends on
- Permit and interconnection timelines
- Equipment availability
- Structural, roofing, and electrical scope
- Installer capacity and weather
Risks and trade-offs
- A firm-looking date may omit utility approval or inspection, leaving the system unable to operate.
- Accelerating work can increase coordination errors or result in incomplete documentation.
Information you may need
- Detailed project schedule
- Permit and interconnection status
- Equipment order or availability confirmation
- Definition of completion and delay remedies
Your next step
What to do next
Request a milestone schedule showing dependencies, responsible parties, contingencies, and the exact event that counts as completion.