How can an interconnection study change the final size or cost of a solar project?

Answer

An interconnection study can require a smaller export level, different inverter or protection equipment, storage or controls, a service upgrade, or utility network work. These findings can reduce the feasible system size, add cost and delay, or make a proposed design uneconomic.

Key points

  • Separate the project's desired generation size from the export capacity the utility will approve.
  • Study costs and upgrade obligations may be assigned to the project under the applicable process.
  • A redesign with lower export, managed output, or storage may avoid some upgrades but can reduce production value.

What it depends on

  • Utility network capacity and protection requirements
  • System size, inverter settings, and point of interconnection
  • Existing site load and export profile
  • Cost allocation and study procedures

Risks and trade-offs

  • An early quote may exclude utility-required upgrades.
  • Network upgrades can have uncertain scope, timing, and cost until the study is complete.
  • Reducing system size may preserve schedule but reduce expected savings or revenue.

Information you may need

  • Preliminary and final interconnection study results
  • Utility cost estimate and upgrade responsibility
  • Alternative designs with export controls or storage
  • Updated production and financial model

Your next step

What to do next

Make the contract contingent on interconnection approval and require a written change-order process for study-driven redesigns and upgrades.