Answer

Confirm the utility-approved export capacity and point of interconnection rather than relying on the equipment's nameplate rating. The utility may limit output because of service capacity, circuit conditions, protection requirements, transformer loading, or export rules.

Key points

  • Compare array DC rating, inverter AC rating, export setting, and approved interconnection capacity.
  • Ask whether the approval permits full output under all operating conditions or requires controls or curtailment.
  • Confirm whether storage, future expansion, and multiple generation sources are included in the study.

What it depends on

  • Utility interconnection approval
  • Service and circuit capacity
  • Inverter controls and protection design
  • Existing and planned generation or storage

Risks and trade-offs

  • Output limits can reduce production and financial returns.
  • Required upgrades or controls can add cost and delay.
  • A contract based on full rated output may overstate expected operation if approval is conditional.

Information you may need

  • Written interconnection approval or preliminary review
  • One-line diagram and equipment ratings
  • Export-control and curtailment specifications
  • Updated production model using the approved limit

Your next step

What to do next

Obtain written utility confirmation of the maximum allowed export and require the quote to model that limit.

Path-Q