What should I check if a solar quote assumes automatic approval for grid connection?
Answer
Treat automatic approval as an unverified claim. Check the utility's actual screening category, application status, technical requirements, approval conditions, and permission-to-operate process before relying on the quote.
Key points
- Ask whether the installer has submitted an application and request the utility case number or written confirmation.
- Confirm that the quoted equipment, size, export level, and point of connection match the submitted design.
- Check whether approval is conditional on upgrades, export limits, protection settings, or meter changes.
- Require the contract to state who pays if approval is delayed, denied, or requires redesign.
What it depends on
- Utility interconnection rules
- System design and export capacity
- Application status
- Service and feeder conditions
- Contract contingencies
Risks and trade-offs
- Assumed approval can conceal significant upgrade cost or delay.
- Changing equipment after application may invalidate or alter the review.
- A low quote may exclude utility, engineering, or redesign costs.
Information you may need
- Utility application record
- Submitted technical documents
- Written approval or screening result
- Upgrade and export-limit conditions
- Contract change-order provisions
Your next step
What to do next
Ask the utility to confirm the project's actual interconnection status and do not accept an automatic-approval assumption as a contract commitment.