What should I check if a solar quote assumes automatic approval for grid connection?

Answer

Treat automatic approval as an unverified claim. Check the utility's actual screening category, application status, technical requirements, approval conditions, and permission-to-operate process before relying on the quote.

Key points

  • Ask whether the installer has submitted an application and request the utility case number or written confirmation.
  • Confirm that the quoted equipment, size, export level, and point of connection match the submitted design.
  • Check whether approval is conditional on upgrades, export limits, protection settings, or meter changes.
  • Require the contract to state who pays if approval is delayed, denied, or requires redesign.

What it depends on

  • Utility interconnection rules
  • System design and export capacity
  • Application status
  • Service and feeder conditions
  • Contract contingencies

Risks and trade-offs

  • Assumed approval can conceal significant upgrade cost or delay.
  • Changing equipment after application may invalidate or alter the review.
  • A low quote may exclude utility, engineering, or redesign costs.

Information you may need

  • Utility application record
  • Submitted technical documents
  • Written approval or screening result
  • Upgrade and export-limit conditions
  • Contract change-order provisions

Your next step

What to do next

Ask the utility to confirm the project's actual interconnection status and do not accept an automatic-approval assumption as a contract commitment.