What information should I obtain about grid export rules before sizing solar?

Answer

Before sizing solar, obtain the utility's current export-credit rate, system-size and export limits, interconnection requirements, credit treatment, and any rules that could change after approval. These facts determine whether a larger system produces useful value or mainly creates lower-value exports.

Key points

  • Ask how exported energy is valued and whether the rate differs from the import rate.
  • Confirm whether export capacity is limited separately from installed solar capacity.
  • Check application, inspection, meter, and permission-to-operate requirements.
  • Ask whether batteries, export controls, or curtailment are required or permitted.

What it depends on

  • Utility tariff and interconnection rules
  • Existing electrical service capacity
  • Proposed inverter and battery configuration
  • Expected production and on-site consumption

Risks and trade-offs

  • A system may be physically capable of producing more than it is allowed to export.
  • A larger array can have diminishing financial value when exports receive low compensation.
  • Adding export-control equipment can affect design, cost, and operating behavior.

Information you may need

  • Current tariff and export-credit schedule
  • Maximum allowed inverter, array, and export capacity
  • Interconnection application requirements and timelines
  • Rules for batteries, curtailment, and future rate changes

Your next step

What to do next

Request the utility's current interconnection and export documents before accepting a system design, then ask the installer to model the design against those constraints.