How should I compare solar proposals when one includes an assumed rebate and another does not?
Answer
Compare both proposals first on a rebate-excluded basis, then show the rebate as a separate conditional scenario. Verify whether the rebate exists, who applies for it, when it is paid, and what happens if it is denied or exhausted.
Key points
- Use the same gross system price, financing costs, production assumptions, and operating costs for both proposals.
- Treat an unconfirmed rebate as zero in the committed-cost comparison.
- Show whether the rebate reduces the contract price, is paid later, or is retained by another party.
- Check application, reservation, installation, equipment, income, property, and deadline requirements.
What it depends on
- Current rebate program rules
- Program funding and availability
- Project and applicant eligibility
- Installer application responsibilities
- Payment timing and contract terms
Risks and trade-offs
- A rebate may be unavailable, delayed, reduced, or subject to post-installation review.
- A lower advertised price may depend on an incentive the customer must secure independently.
- Using rebate proceeds to fund the project can create a cash-flow gap.
Information you may need
- Official program terms
- Written reservation or approval
- Contract treatment of the rebate
- Gross and net pricing
- Deadline and payment timing
Your next step
What to do next
Request revised proposals with identical gross-price assumptions and a separate line showing only verified rebate benefits.