How should I compare installation timelines when one quote depends on utility approval first?
Answer
Separate installer-controlled work from utility-controlled approval, compare the full critical path, and require each quote to state assumptions, milestones, and responsibility for delay.
Key points
- List design, permitting, equipment procurement, installation, inspection, utility review, meter or interconnection work, and permission to operate separately.
- Compare estimated durations and the conditions that start or stop each period.
- Ask whether the price, financing, incentives, or cancellation rights change if approval is delayed or denied.
What it depends on
- The utility's interconnection process and queue
- Permit and inspection requirements
- Equipment availability and installer scheduling
Risks and trade-offs
- A shorter advertised installation period may exclude utility approval and permission to operate.
- Ordering equipment before approval can create cancellation, storage, or redesign risk.
- Delaying installation until approval may reduce some risk but extend the project.
Information you may need
- A milestone schedule with responsible party for each step
- Approval dependencies and estimated ranges
- Delay remedies, cancellation rights, and financing start date
- Confirmation of the conditions for system operation
Your next step
What to do next
Ask both installers to provide a common critical-path schedule that separately identifies utility, permitting, procurement, and installer-controlled time.