Answer
Measure solar generation and site consumption at separate points, using time-synchronized interval data, rather than inferring solar output from changes in the utility bill. Compare the solar meter or inverter production data with a whole-site consumption meter and the utility meter over the same intervals.
Key points
- Solar production is the energy generated by the array; consumption is the energy used by the facility; imports and exports are the net result of both.
- Use revenue-grade or otherwise suitable production and consumption meters when billing, performance guarantees, or disputes depend on the result.
- Align timestamps, units, time zones, demand intervals, and meter multipliers.
- Compare working-hour and non-working-hour periods to identify schedule effects, curtailment, or unexpected baseload.
What it depends on
- Meter locations and measurement boundaries
- Interval length and data quality
- Utility billing and export-meter configuration
- Operating schedule and other on-site generation or storage
Risks and trade-offs
- A utility bill may show net imports or exports and cannot by itself prove solar production.
- Mismatched timestamps or meter settings can create false performance conclusions.
- Additional metering improves evidence but adds installation, communications, and maintenance cost.
Information you may need
- Inverter production data
- Whole-site interval consumption data
- Utility import and export meter data
- Operating schedule and known baseload
Your next step
What to do next
Request a time-aligned interval-data report from the inverter, site meter, and utility, or install separate production and consumption meters if those data are unavailable.
Path-Q